The latest news in Eastern Visayas region

 
 
more news...
 
23rd Yen highways cementing project a landmark in PGMA’s infra program

Mass evacuation in Giporlos communist-instigated, army spokesman says

6 architectural heritage sites in Leyte identified

City government reiterates ban on interment at old cemetery

“Loopholes in party-list law” Babae Ka blames Akbayan’s inaction

One more top ranking NPA leader in Leyte falls

Former speaker Nicanor E. Yñiguez, 92

Over 1.8K landowners in Region 8 receive Free Patents

“Noynoy” lauds Icot’s drive for better hotels in Leyte

 
 

 

 

 

SAMELCO II’s rural electrification hits 92%

By ELI C. DALUMPINES (PIA Samar)
April 20, 2007


GM Rosales (left) answers queries from the local media during a press conference held Thursday at the SAMELCO II compound in Paranas, Samar. At right is Board vice-president Alfonso Quilapio.

CATBALOGAN, Samar  –  Almost all the villages in Samar ’s 2nd district, including those in the interior, are now enjoying the blessings modern technology brings after the government extended to them the power services through its rural electrification program.

Samar II Electric Cooperative (SAMELCO II) General Manager Ponciano Rosales, in a media forum Thursday, reported that his office has already hit 92% of its rural electrification target as of March 6, this year.

According to Rosales, SAMELCO II has already energized 481 barangays out of the 524 barangays under its service area which covers all the 16 towns in the 2nd district, including the island towns of Daram and Zumarraga.

GM Rosales said only 43 barangays under SAMELCO II’s service area remain un-energized as of press time but he informed that work programs for the electrification of these barangays are already lined up.

He further informed that SAMELCO II has set to complete the electrification of the remaining un-energized barangays by 2008.

The summary report of the Cooperative showed that among the 16 towns it covered, Calbiga has the highest number of still un-energized barangays. Fourteen out of the 41 barangays of Calbiga have yet to be energized, the report said.

Meanwhile, SAMELCO II has already made preparations for the upcoming elections this May.

GM Rosales said a task force was already formed to address possible power interruptions in the day of the elections.