Catarman-Calbayog road 
          via Lope de Vega road section already 94% complete
          
          By Philippine Information Agency (PIA 8)
          February 
          21, 2007
          
          TACLOBAN CITY, Leyte 
           –  The Catarman-Calbayog Road via Lope de Vega Road Section which is 
          under the arterial road link development project, Phase V, of 
          President Gloria Macapagal-Arroyo, is already 94 percent complete as 
          of January 25, 2007.
          
          This was reported by 
          the Project Monitoring Committee during the Regional Development 
          meeting last week.
          
          The project which is 
          under the supervision of the Department of Public Works and Highways 
          consist of the improvement and upgrading of at 68.30 kilometers of 
          road connecting Northern Samar and Samar provinces.
          
          With this road 
          construction with the original budget of P621.279 Million and revised 
          to P 643.720 Million, commuters will be able to save about two hours 
          traveling time from Tacloban to Catarman.
          
          The Project Monitoring 
          Committee reported that the occurrence of heavy rains which resulted 
          to flash floods, brought severe damage to the project as well as to 
          the plant and equipment of the contractor.
          
          The Project started on 
          May 31, 2004 and was supposed to be completed in May of 2006. However, 
          because of the aforementioned reasons, the date of completion was 
          reset to October 15, 2006.
          
          Later, it was again 
          reset to December 29, 2006. Unfortunately, in December particularly on 
          the very same date, 29th, several Northern Samar municipalities, 
          including Lope de Vega suffered flash floods once more, and so the 
          date of completion has been further reset to April 25, 2007.
          
          The Monitoring 
          Committee also reported that when the weather is good, the road is 
          already passable. However, for miscellaneous items like the pavement 
          markings, regulatory and directional signs as well as reflectorized 
          paints, the contractor has yet to submit samples for the required 
          quality control tests.