Catarman-Calbayog road
via Lope de Vega road section already 94% complete
By Philippine Information Agency (PIA 8)
February
21, 2007
TACLOBAN CITY, Leyte
– The Catarman-Calbayog Road via Lope de Vega Road Section which is
under the arterial road link development project, Phase V, of
President Gloria Macapagal-Arroyo, is already 94 percent complete as
of January 25, 2007.
This was reported by
the Project Monitoring Committee during the Regional Development
meeting last week.
The project which is
under the supervision of the Department of Public Works and Highways
consist of the improvement and upgrading of at 68.30 kilometers of
road connecting Northern Samar and Samar provinces.
With this road
construction with the original budget of P621.279 Million and revised
to P 643.720 Million, commuters will be able to save about two hours
traveling time from Tacloban to Catarman.
The Project Monitoring
Committee reported that the occurrence of heavy rains which resulted
to flash floods, brought severe damage to the project as well as to
the plant and equipment of the contractor.
The Project started on
May 31, 2004 and was supposed to be completed in May of 2006. However,
because of the aforementioned reasons, the date of completion was
reset to October 15, 2006.
Later, it was again
reset to December 29, 2006. Unfortunately, in December particularly on
the very same date, 29th, several Northern Samar municipalities,
including Lope de Vega suffered flash floods once more, and so the
date of completion has been further reset to April 25, 2007.
The Monitoring
Committee also reported that when the weather is good, the road is
already passable. However, for miscellaneous items like the pavement
markings, regulatory and directional signs as well as reflectorized
paints, the contractor has yet to submit samples for the required
quality control tests.