The latest news in Eastern Visayas region
 
 

Follow samarnews on Twitter

 
more news...

8th ID honors its exemplary soldiers

Cayetano pushes for continuance of 2004 and 2007 poll fraud Senate inquiry

Culture meets contemporary in City's kick-off program

BARECO farmers raise rice harvest from 80 to 178 cavans

VP Binay - Heidi Mendoza audit task force politically motivated; brains behind demolition job “insecure”

“Look Them Straight in the Eye”

Pag-IBIG cuts interest rate for calamity loans - VP Binay

Assistive devices given anew to PWDs in Leyte

 

 

 

 

 

 

DPWH Leyte II reports 84.42% accomplishment on FY 2012 regular infra projects

By Philippine Information Agency (PIA 8)
August 5, 2012

TACLOBAN CITY  –  The Leyte Second Engineering District of the Department of Public Works and Highways has an overall actual accomplishment of 84.42 percent on Fiscal Year 2012 regular infrastructure projects.

This impressive accomplishment has been realized under the leadership of District Engineer Ma. Margarita C. Junia with the strong support by the Assistant District Engineer Joel Melchor R. Boco and the section chiefs of the district engineering office.

The Leyte II Engineering District 2012 regular infrastructure projects amounted to P231.170 Million, DE Junia informed.

The Leyte II District Office has completed 8 projects while another 4 projects were ongoing and one project under the Water Supply/Retarding Basins/Rain Collection and Sewerage.

DE Junia identified the completed projects as the Road upgrading of Burauen-Mahagnao road which amounted to P19.464 million; the upgrading of the Jaro-Dagami-Burauen-La Paz road which amounted to P16.650 million; and the rehabilitation and repair of Palo-Carigara-Ormoc Road with a funding of P30.377 million.

Also completed were the road reblocking with asphalt overlay along Daang Maharlika Kilometer 950+000-Kilometer 951+ 012; Km 958+000-Km 958+804 which amounted to P20.177 million; road reblocking with asphalt overlay along Daang Maharlika Km 945+000-Km 945+291 amounting to P2.117 million; reblocking with asphalt overlay along Palo-Carigara-Ormoc Road amounting to P20.739 million; reblocking with asphalt overlay along another portion of Palo-Carigara-Ormoc Road amounting to P5.992 million; and road reblocking with asphalt overlay along Jaro-Dagami-Burauen-La Paz road amounting to P4.650 million.

Meanwhile, the on-going projects are the Road Upgrading of Bagahupi-Sta. Cruz-Barugo-Carigara Road amounting to P24.978 million; the Kiling, Tanauan-Tabontabon-Julita Road amounting to P36.961 million; the Road Opening of Bagahupi-Babatngon-Sta. Cruz-Barugo-Carigara Road at the Highway Boundary of Leyte 1 and 2 amounting to P26.220 million; and the Road Upgrading of another portion of Kiling-Tanauan-Tabontabon-Julita road amounting to P21.735 million.