BILECO to conduct
public hearing on application for approval of 2011-2016 capital
expenditure program, authority to secure loan
By RODRIGO S. VICTORIA, PIA Biliran
January
9, 2012
NAVAL, Biliran – The
Biliran Electric Cooperative, Incorporated (Bileco) will hold a public
hearing that will involve the future financial outlook and how it will
relate to the improvement in the delivery of quality services of the
lone electric cooperative in the province of Biliran.
The public hearing is
scheduled on January 24, 2012 at around
10:00 o’clock in the morning to be held at the Bileco main office located
in Barangay Caray-Caray, Naval, Biliran, according to a Bileco press
statement dated
January 5, 2011
furnished to PIA.
The public hearing
will tackle the Energy Regulatory Commission (ERC) Case No. 2011-157
entitled “In the matter of the application for approval of capital
expenditure program for the years 2011-2016 with prayers for authority
to secure loan from the National Electrification Administration (NEA)
and provisional authority”, it said.
The press statement
added that Bileco’s capital expenditure application was already
published in Leyte-Samar Daily Express on November 23, 2011 and order
and notice of public hearing was also published on January 2 and 9,
2012 in Philippine Daily Inquirer. Copy of capital expenditure
application and notice of public hearing were furnished also to the
local government units in the province.
The Bileco press
release prepared by Maria Theresa Sambitan, MDO/BAPA Coordinator and
approved by Samuel G. Trinidad, Jr., ISD Manager also invited the
electric cooperative’s member-consumers to attend the public hearing
for them to be able to know the objective of the capital expenditure
project that will be implemented by Bileco to improve its facilities
and to ensure its continued good service.
It mentioned also that
the ERC delegation will be led by Commissioner Alfredo J. Non who will
preside the public hearing that will be conducted.
Meanwhile, in the ERC
application for approval of capital expenditure program for the years
2011-2016 of Bileco, the projects are as follows with its
corresponding total project cost: substation sub-transmission
development projects - P54,378,211; primary distribution development
projects - P21,425,326.50; asset renewal projects - P7,777,386.30;
other capital expenditure: network projects - P19,063.587.70; other
capital expenditure: non-network projects institutional development (ISD)
- P4,359,900; other capital expenditure: non-network projects finance
services department (FSD) - P3,275,819.8; other capital expenditure:
non-network projects technical services department (TSD) - P3, 209,661.90. The grand total of the network and
non-network projects is P113,358,561.22.
Some of the big
projects to be undertaken by Bileco that are part of the 2011-2016
capital expenditure program include the construction of 69KV
sub-transmission line (Biliran to Caray-Caray, Naval) 16.5 kms.,
construction of new substation 3.15MVA at Brgy. Caray-Caray, Naval,
installation of additional line protection for feeder 1 and 2,
construction of double circuit line Caray-Caray-Atipolo Naval (2.8 kms.)
and Caray-Caray-Naval Poblacion (5 kms.), upgrading of distribution
line from 1-phase to 3-phase (Bliss Calumpang to Brgy. Cabibihan,
Caibiran) 20.8 kms., replacement of rotten poles and defective
kilowatthour meter , new connections and distribution transformer
requirement.
Moreover, it was
reflected in Bileco’s application for authority to secure loan that
the total project cost of P116,759,318.07 will be financed through a
15-year term loan from National Electrification Administration (NEA)
with interest of nine percent annually subject to its present lending
policies on loan approval and releases and through internally
generated fund known as Reinvestment Fund for Sustainable Capital
Expenditure.
Out of the total
project cost of P116,759,318.07, P92,159, 378.92 will be sourced out
from NEA and the P24, 599, 939.15 will be sourced out from member’s
contribution for capital expenditures based on the summary of proposed
financiers and the corresponding desired borrowing of Bileco.
Bileco also stated
in its application for approval of 2011-2016 capital expenditure
specifically in item number 8 that the instant capital expenditure
plan was envisioned to have the least rate impact focusing on a
capital expenditure plan that will bring the most value to consumers
at the most reasonable and justifiable electricity rate or at least
cost of service.