93.96% completion on CY 2015 infra projects
By ARDEL S. MALANOG, DPWH
Samar I
January 20, 2015
CALBAYOG CITY – DPWH
Samar I closed CY 2015 with 93.96% actual completion on all
infrastructure projects under General Appropriation Act (GAA).
Posted and verified to
record on December 31, 2015, Samar I concluded the year with an 8.96%
mark over the physical target of 85% on all GAA infrastructure
projects for CY 2015.
Rehabilitation,
reconstruction and upgrading of damaged paved national roads,
construction of diversion roads, bridges and local infrastructures,
roads widening, off-carriage improvement and construction and
maintenance of flood mitigation structures and drainage systems are
among the projects under GAA that were completed in CY 2015. Said
projects have a total programmed amount of P1,425,572,500.
As for projects with
external funding under the Convergence Program, Samar I closed the CY
2015 at 54.05% accomplishment. These projects which include the
construction of classrooms, access roads leading to Calbayog Airport,
Calbayog City as well as the repair and maintenance of national
buildings have an approximate programmed amount of P624,651,000.
Consistent to the assurance
given during the press conference held last November 2015, District
Engineer Virgilio C. Eduarte will continue to monitor and supervise
the remaining projects under CY 2015 with the assistance of the
assigned project engineers.