The
presentation of district engineering offices and regional
office’s accomplishment on the CY 2016 infrastructure projects
wherein Biliran DEO was recognized as the no. 1 top performing
district in the implementation of project during the monthly
coordination meeting of O.I.C. Regional Director, Edgar B.
Tabacon to district engineers and division chiefs on July 19,
2016 at the Regional Office, Baras, Palo, Leyte. The meeting was
hosted by Leyte 5th under OIC District Engineer, Eusebio T.
Culas. |
DPWH-Biliran DEO
no. 1 in the implementation of CY 2016 infrastructure projects
Press Release
July 22, 2016
BILIRAN – The
Department of Public Works and Highways (DPWH)-Biliran District
Engineering Office (DEO) has been recognized by the DPWH Regional
Office 8 as the number one top performing engineering office in the
implementation of the CY2016 infrastructure projects as of June 30,
2016.
This was announced by DPWH
Officer-In-charge (OIC) Regional Director, Engr. Edgar B. Tabacon
during their monthly coordination meeting with District Engineers and
Division Chiefs held at DPWH Regional Office.
Biliran DEO has a total of
66 projects completing 53 projects, 9 on-going and 4 projects still
not yet started with an overall accomplishment of 77.06% as of June
30, 2016. As per record tabulated by the Regional Monitoring Section,
Biliran DEO topped among the 13 District Engineering offices and
Regional Office for the implementation of infra projects.
The Regional Director
commended Biliran DEO District Engineer (DE), David P. Adongay Jr. for
the good job done and advised to keep up the good work. He also
encourage the District Engineers and Chief of the Construction to
exert more effort in order to increase the performance of the Regional
Office.
OIC-RD Tabacon also asserted
that Biliran DEO was the first one to report their accomplishments as
of July, 2016.
Biliran DEO’s status of
implementation of the current infra 2016 CY projects increased with
total accomplishment of 80.33% with 57 projects completed, 5 projects
on-going and 4 projects not yet started as of July 15, 2016.
DE Adongay explained that
the 4 projects are still not yet started because of the delayed
delivery of materials for the projects. The projects which are not yet
started include the repair of National Bridges in the Province with a
total cost of P12M.
As of July 20, 2016, DE
Adongay revealed that the Repair of Looc Bridge project (B00035BR)
along National Road has just started and on-going with laying of water
proofing materials and sealant. The District Engineer advised the
contractor to fast-track the implementation of projects to eliminate
the negative slippages.