                Completed 
                construction of Bagongbong Flood Control (Revetment) along 
                Biliran Circumferential Road, Phase II, Almeria Biliran 
                Province. The project was completed on April 15, 2016 under Chu 
                Construction with a contract cost of P7,702,003.68.  | 
              
            
            
           
          
          High accomplishment 
          on DPWH-Biliran DEO flood control projects
          Press Release
          May 1, 2016
          BILIRAN – The 
          Department of Public Works and Highways (DPWH) -Biliran District 
          Engineering Office (BDEO) are now fast-tracking the completion of 12 
          flood control projects in Biliran before the start of the rainy 
          season. According to District Engineer, David P. Adongay Jr., it is 
          during the rainy season that flooding may likely occur. 
          
          As of April 30, 2016, out of 
          the 12 flood control projects implemented under the 2016 Regular 
          Infrastructure Program, 6 were already completed while remaining 6 are 
          on-going.
          The completed projects are 
          the Mapula Flood Control along Biliran Circumferential Road, Caibiran, 
          Biliran; Bagongbong Flood Control (Revetment) along Biliran 
          Circumferential Road, Phase II, Almeria, Biliran; Bool Flood Control 
          (Revetment) along Biliran Circumferential Road, Culaba, Biliran; Madao 
          Flood Control Structures along Biliran Circumferential Road, Kawayan, 
          Biliran; Tucdao Flood Control along Biliran Circumferential Road, 
          Kawayan, Biliran; and Calambis Flood Control along Biliran 
          Circumferential Road, Caibiran, Biliran.
          Adongay said that they are 
          availing the good weather condition to finish the construction of all 
          flood control projects which has a total appropriation amount of P174 
          million. He also disclosed that the remaining 6 projects are target to 
          be completed in the month of June, 2016. 
          
          To date, the Flood Control 
          Projects has an overall project accomplishment of 66.40% which is high 
          as compared to the target accomplishment of 60% for the month of 
          April, 2016. The completion of the project will help protect the lives 
          and properties of the residents nearby, the hectares of rice fields 
          and at the same time protects the existing Bridges and National Roads 
          within its vicinity.
          Moreover, another 4 
          Revetment projects under the Local Infrastructure Program are already 
          completed which are composed of the P5M Revetment in Sitio Cogon, Brgy. 
          Calumpang, Naval, Biliran; P10M Revetment in Sitio Lomboy, Brgy. 
          Calumpang, Naval, Biliran; P5M Revetment in Anas, Brgy. Agpangi, 
          Naval, Biliran; and P5M Revetment in Anas, Brgy. Atipolo, Naval, 
          Biliran.
          Revetment is one type of 
          flood control structure for protection of the riverbank from collapse 
          brought about by erosion scouring and riverbed degradation.
          Adongay added that the 
          remaining projects are also being fast-tracked and were closely 
          monitored to ensure quality of projects.