| 
                 
                  
                Construction 
                of Slope Protection along Biliran Circumferential Road is 
                on-going with 62% accomplishment as of January 31, 2017. Other 
                than the slope protection structure, concrete paving of widened 
                shoulders and construction of concrete canal are included in the 
                project. The above road section is prone to landslide hence 
                slope protection structure is recommended to prevent recurrence 
                of landslide which happened during the onslaught of typhoon 
                Henry on July 20, 2014 that caused closure of the road.  | 
              
            
            
           
          
          DPWH-Biliran DEO 
          fastracks on-going FY 2016 high impact projects
          Press Release
          February 15, 2017
          NAVAL, Biliran – 
          Above P40M remaining FY 2016 projects implemented by the Department of 
          Public Works and Highways (DPWH) - Biliran District Engineering Office 
          is being fast-tracked for completion until first quarter of 2017. As 
          of January 31, 2017, Biliran DEO reports 63 projects completed with 
          three projects on-going with an accomplishment of 92.64%.
          The District has been 
          allotted P683.745M under FY 2016 DPWH Infrastructure Program. Out of 
          the allotted amount, P135M was implemented by DPWH Regional Office 8 
          which involves the Rehabilitation of a section of Maripipi 
          Circumferential Road, while 66 projects are implemented by Biliran DEO.
          Some District Offices 
          including Biliran DEO has only been allowed to implement projects 
          below P50M, projects above of the said amount are 
          undertaken/implemented by the DPWH Regional Office.
          Adongay reported that two 
          projects of the largest amount allotted to Biliran DEO is still 
          ongoing which is the P45M slope protection project along Biliran 
          Circumferential Road (BCR) and P43M construction of Biliran diversion 
          road with an accomplishment of 62% and 58%, respectively as of January 
          31, 2017.
          According to Adongay, the 
          Construction of Slope Protection along Biliran Circumferential Road 
          encountered some problems caused by lapses of the contractor and 
          unfavorable weather conditions that hinders the contractor to smoothly 
          perform the project implementation.
          Meanwhile, the Construction 
          of Biliran Diversion Road was hindered to proceed with the embankment 
          activities due to continuous heavy rains. Furthermore, one of the 
          landowners affected by the road opening refused to sign “Permit to 
          Enter” for the reason that the amount offered per current market value 
          of his parcel of land is below of what he is expected. The landowner 
          is asking for P2,000 per sq.m. of his land that is affected by the 
          Road-Right-Of-Way (RROW), however, the current market value of an 
          agricultural land is P21.45 only.
          The office is on the process 
          of negotiations with the concerned land owner with regards to the 
          value of the affected parcel of land.
          The completion of the 
          diversion road project will serve the traveling public coming from 
          Tacloban City, Ormoc City, Baybay City and from other neighboring 
          municipalities going to the northern and eastern part of Biliran 
          Province and vice versa in a much safer and faster transport of goods 
          and services and at a reduced travel time. The population to be served 
          by the road ranges from 120,000 to 135,000, 7 Municipalities and 50 
          Barangays.
          Another FY 2016 project 
          eyeing for completion is the on-going P8.7M replacement of permanent 
          weak bridge-Banlas bridge along Maripipi Circumferential Road.
          Adongay revealed that the 
          delay was attributed due to unavailability of sand and gravel 
          aggregates in Maripipi Island. Adongay explained that hauling it by 
          barge with the quantity required is impractical and will only entail 
          higher cost. Hence, the contractor suggested to have the delivery 
          together with the delivery of the sand and gravel for the concreting 
          of Maripipi Circumferential Road.
          Adongay said that the 
          contractors of each projects were advised to render over time work 
          24/7 to complete the projects on the target date.