The latest news in Eastern Visayas region
 

Follow samarnews on Twitter

 
 
more news...

File a complaint with Anti-Red Tape Authority and stop giving bribes – Barba

Poultry workers appeal to food giants: Don’t deal with sweatshops

Biliran DEO orders contractors to fast track delayed projects

TUCP calls for purging of PNP from hoodlums in uniform

Rotary Club of Calbayog facilitates bloodletting activity

NMP attends 2nd and 3rd Quarter PESO Managers Meeting

ALU-TUCP: DOLE's more than 300,000 regularized workers in the SONA report is grossly exaggerated

Review the program, not just the curriculum – ACT

 

 

 

 

 

 

 

DPWH completes flood control extension in Calbayog

Calbayog flood control extension

By ELENOR A. ANOLLADO
August 1, 2018

CALBAYOG CITY – The Department of Public Works and Highways Samar First District Engineering Office (SFDEO) completes the construction and extension of flood control structures in Brgy. Oquendo, Calbayog City.

The P40 million project which was completed last July 18, 2018, consists of 586 meters of flood mitigating structures using structural concrete and reinforcing steel. It is under contract with Victoria Development and Construction Supply Corp.

This project serves as an extension to the existing flood control structures in Oquendo and aims to protect the residents of nearby barangays; Begaho and Nabang. These areas lie adjacent to Jibatang River and are subjected to the abrupt changes in water levels that cause flooding.

“On behalf of our community, we are very thankful to DPWH for completing this flood control project. I’ve been living here for quite a while and I’ve experienced numerous floods throughout my lifetime. As a resident and a business owner, now I don’t have to worry about the flood damaging my goods and property,” said Christine Oñate.