David
P. Adongay Jr. District Engineer of Biliran District
Engineering Office inspects on-going construction of
drainage along Naval-Caibiran Cross Country Road (NCCCR),
Naval, Biliran on May 31, 2018. This project is target to be
completed on September 2, 2018. |
DPWH-Biliran
DEO’s updates on 2018 project status
Press Release
June 13, 2018
NAVAL, Biliran –
The Department of Public Works and Highways (DPWH) –Biliran District
Engineering Office (DEO) continues progress for its 2018 project
implementation. As of May 31, 2018, the office has a total actual
accomplishment of 25.01% with a positive slippage of 0.39%.
P1.6B has been allotted to
Biliran DEO for the implementation of 60 infrastructure projects
based on the 2018 General Appropriation Act (GAA). Out of the 60
projects, 36 are on-going, six are completed and 18 are up for
implementation.
David P. Adongay Jr.,
District Engineer accounted the delay of projects due to the damages
caused by tropical storm Urduja on December, 2017 resulting
inaccessibility to project sites.
Under preliminary and
detailed engineering activities, Engr. Rosario B. Rosete, Chief of
the Planning and Design Section reported that 57 were already
completed while only three are on-going with an accomplishment
96.54% as of May 31, 2018.
The purpose of preliminary
engineering is to gather the necessary data from the field as basis
in the preparation of plans. Activities under this phase includes
surveying, designing and programming.
For pre-construction
phase, out of the 60 projects, 49 are completed, eight are on-going
and three are Not-Yet-Started (NYS) with an accomplishment of 77.98%
as of May 31, 2018.
The district had already
advertised 57 and successfully bid out 56 out of 60 projects under
FY 2018 GAA.
The office continues to
monitor and fast tracks these projects in order to deliver a safe
and quality assured infrastructures that will be beneficial to the
end-users.