David
P. Adongay Jr., (wearing jacket) District Engineer inspects
on-going construction of Caraycaray flood control structure
project in Naval, Biliran. |
District engineer
Adongay addressed slow implementation of projects of DPWH-Biliran
Press Release
October 4, 2018
NAVAL, Biliran –
The Department of Public Works and Highways (DPWH) Biliran District
Engineering Office (DEO) is urging contractors to fast-track the
implementation of projects to meet the district’s physical target
accomplishment.
David P. Adongay Jr.
District Engineer expressed his disappointment on the low
performance of the district office for the month of September, 2018.
According to Adongay,
Biliran DEO placed number 12 out of the 13 performing districts in
Region VIII for the said month.
As of September 31, 2018,
the district has reported a negative slippage of .70% and has an
overall accomplishment of 59.69%.
Adongay emphasized that
the physical accomplishment of the district from August to
September, 2018 just increased to only .06% when it is supposed to
increase at least 15% each month.
The district engineer is
strongly asking for cooperation from the contractors to help Biliran
DEO accelerate its project implementation.
“Hindi ibig sabihin
pinabibilisan ang projects, macocompromise na ang quality,” Adongay
said.
Adongay also orders
project engineers to closely monitor their projects from time to
time.
In order to patch up the
negative slippage and low accomplishment of the district, Adongay
strictly orders project engineers not to approve any time extension
or suspension requested by the contractor.
Under 2018 project
implementation, Biliran DEO has a total of 60 projects. As of
September 31, 2018, 31 projects are already completed, 26 are
on-going and three are not yet started. Some of the big ticket
projects are still on-going or just started, hence the low
performance.
The district has completed
four rehabilitation of bridges, two asphalt overlay projects, two
access road projects leading to trades and industries and economic
zones and 17 flood control projects under its 2018 regular
infrastructure project implementation. While under 2018 local
infrastructure project implementation, Biliran DEO has completed
three multi-purpose buildings, one flood control project, one
Farm-to-market road project, and one road widening project.