					David 
					P. Adongay Jr., (wearing jacket) District Engineer inspects 
					on-going construction of Caraycaray flood control structure 
					project in Naval, Biliran.  | 
				
			
			 
			
			District engineer 
			Adongay addressed slow implementation of projects of DPWH-Biliran
			
			Press Release
			October 4, 2018
			NAVAL, Biliran – 
			The Department of Public Works and Highways (DPWH) Biliran District 
			Engineering Office (DEO) is urging contractors to fast-track the 
			implementation of projects to meet the district’s physical target 
			accomplishment.
			David P. Adongay Jr. 
			District Engineer expressed his disappointment on the low 
			performance of the district office for the month of September, 2018.
			According to Adongay, 
			Biliran DEO placed number 12 out of the 13 performing districts in 
			Region VIII for the said month.
			As of September 31, 2018, 
			the district has reported a negative slippage of .70% and has an 
			overall accomplishment of 59.69%.
			Adongay emphasized that 
			the physical accomplishment of the district from August to 
			September, 2018 just increased to only .06% when it is supposed to 
			increase at least 15% each month.
			The district engineer is 
			strongly asking for cooperation from the contractors to help Biliran 
			DEO accelerate its project implementation.
			“Hindi ibig sabihin 
			pinabibilisan ang projects, macocompromise na ang quality,” Adongay 
			said.
			Adongay also orders 
			project engineers to closely monitor their projects from time to 
			time.
			In order to patch up the 
			negative slippage and low accomplishment of the district, Adongay 
			strictly orders project engineers not to approve any time extension 
			or suspension requested by the contractor.
			Under 2018 project 
			implementation, Biliran DEO has a total of 60 projects. As of 
			September 31, 2018, 31 projects are already completed, 26 are 
			on-going and three are not yet started. Some of the big ticket 
			projects are still on-going or just started, hence the low 
			performance.
			The district has completed 
			four rehabilitation of bridges, two asphalt overlay projects, two 
			access road projects leading to trades and industries and economic 
			zones and 17 flood control projects under its 2018 regular 
			infrastructure project implementation. While under 2018 local 
			infrastructure project implementation, Biliran DEO has completed 
			three multi-purpose buildings, one flood control project, one 
			Farm-to-market road project, and one road widening project.