The latest news in Eastern Visayas region
 

Follow samarnews on Twitter

 
 
more news...

DAR rehabilitates 10km Tarangnan road

What politics needs most

DAR fulfills dream of Villaba villagers

P10.41 million 3 storey-4 classroom School Building (SB) Project up for completion

Armed fighting in Basilan displaces 17,000 people

DPWH-Samar I participates Pag-IBIG FCC 1st General Assembly

Youth group welcomes SC TRO on curfew, calls for continued vigilance

SC decision on EDCA reaffirms need to assert sovereignty - Karapatan

 

 

 

 

 

Almeria National High School
The newly completed construction of 2-storey 6-classroom Senior High School Building at Almeria National High School, Almeria, Biliran. The project was under contract with CNE Construction with a contract cost of P8,214,965.05. The completed project will be utilized by more or less 240 Senior High School students.

DE Adongay eyes completion of the 2016 senior high school building projects

Press Release
August 5, 2016

BILIRAN – The Department of Public Works and Highways (DPWH) - Biliran District Engineering Office (BDEO) is target to finish all Senior High School buildings in the entire province of Biliran by August or September this year.

District Engineer, David P. Adongay Jr. during the Kapihan: Pulong-pulong ng Bayan on Radyo Natin FM said that the target completion of the school building projects which supposedly be finished by June before opening of classes was extended due to the failure of the sub-soil exploration test. Engr. Adongay clarified that the completion of the Senior High School Buildings are dependent on the result of the subsoil exploration test and the release of the additional funds.

“Meron kaming mga projects na nabid-out na but ang nangyari during the subsoil exploration test ay nagfail, so irere-design namin yan so additional funding yan, nirequest namin sa higher authorities kasi mag-iiba yung foundation niya, mas tataas yung volume niya ng concrete at mas lalalim ang kanyang excavation works so until now hinihintay pa namin yan (release of funds).”

Engr. Adongay points out that the main problem in the implementation of school building projects are the site identified by the DepEd. The district engineer suggested that DPWH and DepEd should have a joint evaluation and identification of building sites because its terrain is one to be considered in the budget allocation.

“Kaya dapat talaga sa identification palang ma-identified namin kung ano talaga ang dapat tatrabahuin diyan for example yung leveling, yung scope of work sa excavation, aside sa subsoil exploration,” Engr. Adongay said.

As of July, 2016, Engr. Adongay reported that Biliran DEO have already posts 59.43% for the school building projects. Out of the 30 school buildings projects, 11 are already completed, 4 not yet started, 5 are still on-going and 10 are substantially completed. Adongay explained that they still didn’t allow classes to hold on those substantially completed buildings to ensure the safety of teachers and students.

“Nagawa na namin yung revise kaya lang walang pondo, ang required sa amin ay completion talaga nang buong building mahirap naman gagawa tayo diyan tapos walang ceiling, pintura, parang hindi maganda. At least yung dini-deliver namin na school building yung conducive to learning at maganda talaga,” said Engr. Adongay.