Access road
connecting Villa Caneja-Sitio Kahukaw in support of food and
resource-based processing underway
Press Release
December 7, 2018
NAVAL, Biliran –
The Department of Public Works and Highways (DPWH) Biliran District
Engineering Office (DEO) nearly completes the construction of P32.2M
access road leading to trades and industries in support of the food
and resource-based processing in Sitio Kahukaw.
In partnership with the
Department of Trade and Industry (DTI), Biliran DEO is currently
implementing the concreting of 3.6-kilometer existing earth road
with slope protection structure that will connect Barangay Villa
Canejato Sitio Kahukaw in the same barangay in the town of Naval.
David P. Adongay Jr.,
District Engineer said that the project was prioritized in order to
bring their processed ginger powder, abaca helm, coconut-based
products, and atchara to the market center in the progressive town
of Naval and to the nearby urban areas.
From a hilly and bumpy
road, residents in Sitio Kahukaw will directly benefit the project
giving them a safe travel and fast transport of their local
products.
Adongay said that thru
better roads leading to trades and industries, more locals will be
encouraged to do business that will create an additional livelihood
and an additional income.
Under the Special
Convergence Program of the DPWH and DTI, five project are
implemented for the construction/ improvement of access roads
leading to trades, industries and economic zones with a total cost
of P133.972M. Out of the five projects, two are already completed,
while 3 are on-going.
As of November 30, 2018,
the construction of access road connecting Villa Caneja to Sitio
Kahukaw has an accomplishment of 95%. This project is eyed for
completion on December, 2018.
Also up for completion are
the construction of P25M access road, Villa Caneja- Anislagan Road
connecting to Anislagan Ceramics Producers Association (ACPA) and
the P25M National Road Junction (NRJ) Agpangi connecting to Sitio
Pongon all in Naval.
Meanwhile, the P30M
construction of access road, (NRJ) Villa Consuelo connecting to
Libtong Road and P18.9M access road, Caraycara -Cabungaan-Libtong
Road are already completed.